RamonaValenzuelaPerez - 2012-06-21
Proton Detector
Summer Data Collection
- Diagnostic installation: July 1st - July 15th 2013
- Data collection: July 16th - July 26th 2013
- Parasitic data collection: July 27th - End of M9 Camp 2013
Preliminary Noise Testing
March 19th, 2013 Group Discussion
Noise Testing Information, March 2013
Collaborators travelling to MAST:
- Ramona Perez: March 11th - March 24th 2013
- Werner Boeglin: March 11th - March 15th 2013
- Doug Darrow: March 11th - March 20th 2013
Radiation Source Use - Method Statments:
Electronics Schema:
Drawings - Mechanical Design 2013
- This reflects new length of 185mm and new diameter of 96mm
- Coming soon (changes to probe head orientation angles as during Noise Testing)
Prototype
Installation: January 2013
Comments:
- Prototype type dimensions fit into RP access cube (reduction in probe head diameter requested for greater ease of installation)
- Our prototype RP connector may have become distorted during the welding of the connector to the prototype shell (this issue was fixed at CCFE)
- A dummy RP shaft end was created and sent to FIU to test the fit of the RP connector before bringing the diagnostic for the summer data collection
- Vacuum vent hole had to be drilled in top of prototype to bake for RP installation (at CCFE)
Machine Drawings:
Mechanical Design Review
MAST Mechanical Design Review Materials, September 9th 2012
Presentation:
Machine Drawings:
Supporting Documents (for reference if needed):
Mechanical Design Overview after June 26 2012 MAST Colleagues Discussion
Mechanical Design Overview after June 19 2012 Meeting with PPPL Colleagues